The Use and Principle of Current Transformer Acrel Support Olympic Winter Games Beijing 2022 Power Supply Solution for Winter Olympics Wireless Temperature Solution at Beijing Daxing International Airport Acrel Releases ADW300 with 333mV Access Energy meters used in urban comprehensive pipe gallery projects Working Principles and Wiring of Various Types of Electric Meters Digital Electric Energy Meter VS Electronic Electric Energy Meter Problems and Common Fault Analysis of Current Transformers During Operation Detection and Marking of Current Transformers The Functions and Working Principles of Current Transformers Application of DC Current Meters in Substation DC Measurement Operation Methods and Precautions of Current Transformers The Detection and the Open Circuit Fault Inspection of Current Transformers Models, Structures and Installation Methods of Different Hall Current Sensors The Working Principles of the DC Current Shunts How to Set the Temp and Humidity Controller? Precautions of Multifunction Meter Storage Principle and Characteristic Parameters of Hall Current Sensor Multi-function Instrument Definition and Troubleshooting The Use of Prepayment Energy Meter and Its Advantages over Induction Meter Basic Functions of Smart Prepaid Electricity Meter in Student Dormitories How to Use the Multi Function Energy Meter? What Functions Does It Have? Factors That Affect the Performance and Use Value of Prepayment Energy Meter Application of ​IoT Based Electricity Energy Meter Application of Wireless Temperature Sensor in Press What is the Significance of Smart Energy Meter Applications? Smart Energy Meter Application What Are the Common Faults of Current Transformers? Operation Precautions of Current Transformers and the Cause of Burning The Principle and Use of Through-core Current Transformers The Wiring Principle of Current Transformers Design Features of Wireless Temperature Sensors Errors of Daily Current Transformers

The Principle and Use of Through-core Current Transformers


1. The principle of through-core current transformers


The feed-through current transformer itself is not a primary winding, and the current-carrying (load current) wires from L1 to L2 pass through a circle (or other shape) made of silicon steel sheet rolling to play the role of a primary winding. The secondary winding is directly and evenly wound on the circular dead center, and is connected in series with the secondary loads of the current coils such as instruments, relays, and transmitters to form a closed loop.


Since the feedthrough current transformer does not have a primary winding, its transformation ratio is determined according to the number of turns that the primary winding passes through the dead center of the current transformer. , the larger the transformation ratio, the ratio of the rated current: in the formula I1——a rated current when one turn through the center; n——the number of turns through the center.


Compared with the common CT current transformer, the wiring of the through-core current transformer, the primary side passes through the P1 side of the transformer, and the P2 side comes out, and the secondary side wiring is the same as that of the common current transformer.


During the measurement, the circuit impedance of the secondary circuit of the current transformer is very small, so the secondary circuit of the current transformer is close to a short circuit, and in order to unify the standard, the rated value of the secondary winding is generally designed to be 5A. In practical applications, for safety consideration, the secondary side S2 of the current transformer generally needs to be grounded.


2. Correct use of through-core current transformers


Feed-through current transformer is a common electrical device with simple wiring and convenient installation. It is widely used in metering, testing and maintenance lines. If you are not careful during use, it will cause great errors, resulting in inaccurate measurement, maintenance failure, and electrical accidents. Therefore, you should pay attention to the use method.


The transformation ratio of the current transformer should meet the requirements of the load current, and the normal load current should be 1/3 to 2/3 of the primary rated current of the current transformer. A current transformer with an accuracy level of 0.2S or 0.5S should be selected.


When piercing the heart, the terminal marked "L1" or "+" in the primary circuit should be connected to the incoming power line, and the terminal marked "L2" or "-" should be connected to the outgoing wire. The terminal marked with "K1" or "+" in the secondary circuit should be connected with the incoming terminal of the current coil of the electric energy meter, and the terminal marked with "K2" or "-" should be connected with the outgoing terminal of the electric energy meter.


The key to the use of feed-through current transformers is that the number of turns of the feed-through must be correct, not only the conversion ratio indicated on the nameplate, but also the number of turns of the feed-through. The number of feed-through turns is equal to the ratio of the primary side current when the feed-through turns is one turn to the primary side current corresponding to the conversion ratio.


The terminal, shell and iron core of "K2" or "-" of the secondary circuit of the current transformer must be grounded stably.


Related Articles about Acrel